With reference to the scenarion I run in the test system, when the SKIP lot was created at GR, the material was posted directly to UNR and not to quality and this was without running the auto UD job.
I want to know that is this system behaviour correct where the lot with SKIP status is held at quality and will need a QA10 job to clear it ? As per the functionality for skip lot.. the first lot is quality heald and the 9th lot with the settings as per the DMR. But in this case the lot is generated with SKIP status and then stuck in quality.
Also I checked for the
a) No inspection plan assigned yet to this material as it's not created itself.-->insp plan is created before 2 years so no issue with that.
b) Checkbox active to Trigger sample calculation manually, in QM view for material master.--No check box is not active.
c) Inspection with task list/Material Spec/By Configuration not sele
>in place
d) Automatic Assignment for inspection plan is not selected in QM view.--> selected
c) Multiple inspection plans added to the same material, and all are 'Active' at the same time, confusing the system to pick the right inspection plan form the list..!!, etc---> but this has not happened in my case